ProzessTiangong LCADatensatzversion: v01.01.001

Secondary copper production; Two-stage method - blast furnace smelting; Mixed production; In the factory [en]

Datenquelle: Tiangong LCA Data Working Group [en]

Referenzprodukt
Blister Copper [en]
Funktionelle Einheit
1000 kg
Region
China (CN) · Geografische Genauigkeit nicht angegeben
Referenzjahr
2006

Datensatzbeschreibung

Product systems related to equipment and infrastructure (including transportation vehicles, machinery, factory buildings, etc.) are not within the scope of the study.The energy sources such as electricity and steam are regarded as the energy input from the environment to the system. The environmental load brought by the generation of these energy sources depends on the amount of electricity and steam used, and is included in the environment of the process by analogy The load is on. The transportation journey is calculated based on a 3t heavy-duty truck with a capacity of 100 km. The treatment process of waste water and solid waste is not considered. Auxiliary materials with an environmental impact of less than 5% (such as quartz) are not considered. [en]

Technologiebeschreibung

The technical core of the two-stage method for treating waste and impure copper lies in the two-stage pyrometallurgical process of "reduction smelting to remove zinc and tin" and "oxidation refining to remove impurities", which gradually purifies the complex waste and impure copper into qualified anode copper, and finally electrolyzes it to produce cathode copper. [en]

Datensatz

Klassifikation
ILCD · C · Manufacturing; ILCD · 24 · Manufacture of basic metals; ILCD · 242 · Manufacture of basic precious and other non-ferrous metals; ILCD · 2420 · Manufacture of basic precious and other non-ferrous metals